Preventive Maintenance Metrics

FMX PM Performance · Rolling 24-month window · Building 110428
Occurrences: 2911 total · 2043 included · 868 safety-excluded
Last pulled: 2026-10-16 19:45 UTC
← PM tasks · Unplanned metrics →
On-Time Performance

Fair-Rite policy: PM is due within 7 business days after it triggers (weekends and company holidays don't count). The headline rate counts anything completed within that grace as on-time, matching Phil's quarterly KPI methodology.

On-Time Rate
98.8%
2013 of 2038 completed within 7-day grace
Strict (No Grace)
66.2%
1349 of 2038 completed on/before trigger
Open & Overdue
1
past 7-day grace, not yet completed
Total Occurrences
2043
in rolling 24-month window
Volume by Month (24-month trailing)

PM Occurrences Created per Month

Quarter-over-Quarter On-Time Rate

Strict (blue) vs Lenient (green, ≤7d grace)

Completion State Mix (Rolling Window)

Where Every Occurrence Landed

Top 10 Users by Volume
User IDTotalOn TimeOverdueRate
618448 1040 731 309 70.3%
676967 311 235 76 75.6%
683520 189 96 93 50.8%
674956 156 107 49 68.6%
680191 127 46 81 36.2%
617520 92 66 26 71.7%
689372 62 30 32 48.4%
650667 22 9 13 40.9%
617519 17 16 1 94.1%
672115 7 4 3 57.1%
Worst On-Time Tasks (≥4 occurrences)
TaskTotalOn TimeOverdueRate
Inspect Gutters 4 0 4 0.0%
Summer A/C inspection 7 0 7 0.0%
Printer Inspection 8 2 5 25.0%
Inspection and lubrication Mule 4 1 3 25.0%
Pellet Transfer Conveyor Inspection 12 4 8 33.3%
Pellet Transfer Conveyor Inspection 12 4 8 33.3%
Erich #1 Lubrication 24 10 14 41.7%
Erich #1 Inspection 24 11 13 45.8%
Vaporizer Inspection and Switching 24 11 13 45.8%
Ro Tap Inspection and lubrication 24 11 13 45.8%