Powder / Maintenance

Workload · cycle counts · issues · supplies · improvement ideas
Source: Flat Rock weekly meeting minutes
Latest meeting: Monday, August 17, 2026
Live tickets: /maintenance · /preventive-maintenance

Workload

  • 79 Calcine – passed iron rinse 7/27 – Phase 1 complete
  • 44 Calcine - Scheduled
  • 68 Calcine – Batching
  • 52 in Mill
  • Starting 3 shifts next week for calcine
  • House windows replaced – Jake
  • Light at gate (key pad) - Jake
  • To Do List: fair-rite-products-corp.gofmx.com/maintenance-requests

Cycle Counts

  • August – On Schedule

Time Out

  • Tom 9/1 (1/2 day off PM)

Powder Issues

  • LOI iCAR – pushed out 6 months for a follow-up

Supplies Needed

  • Flag, Rope and Buckles – Jake - on order as of 8/10 (Amber) – coming in 8/17
  • FMX Maintenance Request: https://fair-rite-products-corp.gofmx.com/maintenance-requests/8608882

Improvement Ideas

  • Spray Dryer Update (FMX 7201450) – Target upgrade start date of Sept. 21st